The Environment Agency has completed pump refurbishments at Midelney and Huish Episcopi as part of an £11 million upgrade across six pumping stations on the Somerset Levels and Moors.
Next sites and expected benefits
Work at Northmoor and Westover is due to follow in 2027, with Long Load and North Drain due to be finished in 2028. Many of the area’s 21 pumping stations have equipment installed in the 1960s or 1970s. All 21 already use electric pumps. The agency expects modernised pumps to be more reliable, use less energy, need less maintenance and cause less harm to fish and eels. It did not give measured savings for the completed sites.
Programme funding
The agency describes the work as the first phase of a longer programme to modernise pumping across the Levels and Moors. The £11 million comes from Somerset’s share of the government’s national flood and coastal erosion investment and is separate from the £50 million Defra is investing through Somerset Council.